How to build a disaster recovery plan: a step-by-step guide
Setting RPO and RTO targets, choosing a second site, replication methods and drills: a guide to a disaster recovery plan that actually works.
By: Business Continuity Team
Many organizations with a disaster recovery plan have never tested it. An untested plan is like software run for the first time on the day of the disaster: it will most likely not work as expected.
1. Prioritize your systems
Not every system is equally critical. Start by listing systems with your business units and assessing the impact of one hour, one day and one week of downtime for each.
2. Set RPO and RTO targets
RPO (Recovery Point Objective) is the maximum amount of data you can afford to lose, expressed in time. RTO (Recovery Time Objective) is the longest acceptable time to bring a system back. Payment systems need an RPO close to zero, while 24 hours may be acceptable for an internal reporting system.
3. Choose the second site
The recovery site should be far enough away not to be affected by the same natural disaster, power grid or carrier failure as the primary site. A distance of at least 200 km is generally recommended. Latency is also a limiting factor if synchronous replication is required.
4. Choose a replication method
- Synchronous replication: zero data loss, but needs short distances and high bandwidth
- Asynchronous replication: RPO measured in minutes, feasible over long distances
- Restore from backup: the most economical method, but RTO can take hours
- Immutable backups: the last line of defense against ransomware
5. Write down the recovery order
Systems depend on each other. There is no point starting application servers before identity, DNS and databases are up. The plan should describe, step by step, in what order and by whom systems are brought back.
6. Run drills and document them
At least twice a year, run a full recovery drill in an isolated network that does not affect production. Compare the measured RTO and RPO with your targets and close the gaps before the next drill. Drill reports are also requested in regulatory and ISO 22301 audits.